900ttransportation and erection integrated machine adopts a three-pronged designingmode with elevation, transportation and erection. It is used to transport anderect prestressed reinforced box girders of 32m, 24m, and 20m (if necessary, itcan also erect non-standard box girders between 20 and 32m) in the high-speedrailway and passenger line. It can pass the hole with the whole set of boxgirders through the tunnel of 250km/h our 350km/h. It can erect girders attunnel portal or even inside the tunnel, the method of which is the same withtasks without tunnels. It can move and erect on the normal pavement, roadbed orfinished box girders without damning anything. It can erect girder on either sideof the girder yard without the problem of transferring sites. Compared withpresent launching girder, it can erect the beam smoothly without the auxiliarymachine, which is of less weight, simple form, needless to be anchored, easyoperation and high efficiency; easy operation in the entire machine’s spantransformation, and has a stronger adaptability for the operating conditions.
Accordingto different mechanical structures, there are 900t Single-beam TransportationAnd Erection Integrated Machine and 900t Double-beam Transportation AndErection Integrated Machine.
Performance and parameters:
Rated lifting weight: 900t
Applicable span: 32m、24m、20m
Entire machine weight: 560t
Dimensions: 92×7.1×9 m(length×width×height)
Inner net width: 3.3m
Erecting girder minimum curve radius: 2000m
Entire machine working level: A3
All the mechanisms working level: M4
Lifting speed: 0.5m/min
Maximum lifting height: 4.45m
Operating speed (no-load) 10km/h
Operating speed (heavy-load) 4km/h
Maximum tire pressure: 22t
Allowable maximum operation longitudinal slope: 3%
Total power: 900kw